Mezzanine steelwork and deck being installed by NXT Level Group
Mezzanine Installation Guide

Mezzanine Installation Guide: What to Expect from Survey to Handover

A step-by-step guide to a typical mezzanine project, from the first site survey to the day you start using your new floor, with realistic timings on site.

  • About 50 square metres a day
  • Work planned around you
  • Qualified installers
Qualified installers holding CITB, IPAF and PASMA cards, registered with SEIRS
Over 20 years designing and installing mezzanine floors
Based in Canterbury, working across Kent, London and Essex
Before you start

A mezzanine is a construction project, done cleanly

A mezzanine floor can double the usable space in part of your building, but it is still a construction project. Knowing what happens at each stage helps you plan around your operation and avoid surprises.

This guide walks through a typical installation by our own qualified installers, drawing on over 20 years designing and installing mezzanine floors.

How long does installation take?

About 50 square metres a day

Our installers fit about 50 square metres of mezzanine a day on a clear site.

Plus about a day for extras

Allow around one more day for staircases, handrails and other extras.

200 square metres in about a week

A 200 square metre floor with a staircase takes about a week on site.

Evenings and weekends

We can work outside your normal hours where needed, at an extra charge.

Mezzanine steel sections arriving on a trailer, by NXT Level Group
On site

Built with minimal disruption

The time on site is often the shortest part of the project. We plan the work around your operation, with phased working where needed and exclusion zones keeping your team safe while work continues nearby.

A project manager oversees your job from survey to handover, and our own installers keep work areas safe, tidy and clearly separated.

  • Phased working around your operation
  • Exclusion zones and site inductions
  • Own qualified installers
  • Evenings and weekends at an extra charge
10 steps

The installation process, step by step

Step 1. Free site survey

One of our team visits your premises to understand how you work and what you need the space for. We check the clear height to the roof, lights and services; the floor slab; existing columns, racking, doors, fire exits and sprinklers; forklift routes and where stairs and pallet gates could go; and how the floor will be used. Book yours through our contact page.

Step 2. Design and quotation

We draw up a layout of the floor showing the column grid, beams, deck, staircases, handrails, pallet gates and any fire protection. You review it, we check column positions against your racking and aisles, and we send a written quotation. See mezzanine design.

Step 3. Structural calculations

Calculations confirm the steel sections, connections and base plates are right for the agreed load. Where racking or machinery sits on the deck, point loads are checked too.

Step 4. Building Regulations

We prepare and submit the drawings, calculations and fire and escape details to a building control body, either your council or a registered building control approver. Read our planning permission and Building Regulations guide.

Step 5. Manufacture

Once the design is approved and the order confirmed, the steelwork is made to the dimensions on the drawings, and the decking, stairs, handrails and gates are prepared.

Step 6. Site preparation

We agree a programme with you covering clearing the area, delivery times and vehicle access, exclusion zones, any isolation of lighting, sprinklers or alarms, and site rules and inductions.

Step 7. Installation

A steel mezzanine is a bolt-together structure, so installation is quicker and cleaner than traditional building work. Base plates are fixed to the slab, columns go up, beams are bolted in and the deck is laid. Staircases, handrails and pallet gates follow.

Step 8. Fire protection and fit-out

Where needed, a fire-rated suspended ceiling is fitted beneath the deck, with casings to columns and fascias to the edges. For office mezzanines we add partitioning, ceilings, doors and finishes, with lighting and power by our trusted electrical partners. Racking or shelving on the deck can go in at this stage too.

Step 9. Inspection and sign-off

Building Control inspects the work to check it matches the approved drawings, including connections, stairs, handrails, guarding and fire protection. We carry out our own quality checks and snagging, and the completion certificate is issued once Building Control is satisfied.

Step 10. Handover

We walk you through the finished floor and hand over the documents: as-built drawings, structural calculations and load rating, a safe working load notice on the mezzanine, the Building Regulations completion certificate, fire protection certificates where relevant, and guidance on use and inspection.

Mezzanine steelwork and joists going in during installation, by NXT Level Group
Handover

Keep your handover documents safe

Insurers, landlords, buyers and future tenants may ask for your handover documents. If you are the responsible person under fire safety law, review your fire risk assessment now that the building has a new floor level.

Adding racking or shelving to the deck? We can arrange SEMA-approved inspections.

  • As-built drawings and calculations
  • Safe working load notice
  • Building Regulations completion certificate
Google reviews

Rated 5.0 on Google

“Amazing work from Robbie and Lance very professional service would highly recommend…”
Perry Keegan
“Very good workers, accurate and well layed out designs, 2nd mez they have done for us…”
Steve Hubbard
“Nxt Level recently installed our mezzanine and I honestly cannot recommend them highly enough…”
Alex Fenner
Keep reading

More guides and services

Mezzanine floor cost guide

What drives the cost of a mezzanine, and how to compare quotes like for like.

Read the guide 

Planning and Building Regulations

When planning permission applies and what Building Regulations cover.

Read the guide 

Mezzanine floors in Kent

Our full mezzanine service, from survey to handover.

Mezzanine floors 

Stairs, handrails and gates

Part K and utility staircases, handrails, pallet gates, decking and protection.

Mezzanine ancillaries 

Our projects

Photos of recent mezzanine, racking and fit-out work across Kent, London and Essex.

See our projects 

About NXT Level Group

A Canterbury team with over 20 years designing and installing mezzanine floors.

About us 

Case studies: JLC Ltd (Jaguar Land Rover), Sevenoaks · Big Fish SRL, Horsmonden · Eurotunnel, Folkestone

Common questions

How long does it take to install a mezzanine floor?
As a guide, our installers fit about 50 square metres of mezzanine a day, plus around a day for staircases, handrails and other extras. A 200 square metre floor with a staircase takes about a week on site.
Can a mezzanine be installed while my business is open?
Usually, yes. Installation is planned around your operation, with exclusion zones keeping your staff safe while work continues nearby.
Can you work evenings or weekends?
Yes. Installation can be planned outside your normal working hours where needed, at an extra charge, so your business keeps running.
What happens during a site survey?
We measure your building, check the floor slab, columns, services and fire exits, and talk through how you will use the space. This sets the design, load rating and approvals needed.
Do I need to clear the area before installation?
The installation area generally needs to be clear. We agree what needs moving, and when, as part of the programme.
Who manages my project?
A project manager oversees your job from survey to handover, and our own qualified installers carry out the work.
What documents do I get when the mezzanine is finished?
Typically as-built drawings, structural calculations, the Building Regulations completion certificate, a load notice, and fire protection certificates where relevant.
Can you move or remove an existing mezzanine?
Yes. We offer mezzanine dismantling and relocation, which can be planned alongside a new installation.

Tell us about your project

Tell us about your building and what the floor is for, and we will arrange your free site survey and a clear programme. Prefer to talk? Call 01227 678 128 or 0330 133 2445.

Please fill out the form below, and we will be in touch as soon as possible.
Select one option

See our privacy policy.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Start your mezzanine project

Book a free site survey and we will give you a clear programme and a written quotation for your premises. Read about costs in our mezzanine floor cost guide. Call us Monday to Friday 8:00 to 17:30, closed weekends, or email info@nxtlevelgroup.co.uk.

Contact us

NXT Level Group
6-8 Longmarket
Canterbury, Kent CT1 2JS
Phone
01227 678 1280330 133 2445
Email
info@nxtlevelgroup.co.uk
Opening hours
Monday to Friday 8:00 to 17:30, closed weekends

Follow us

Areas we cover: Canterbury · Ashford · Maidstone · Medway · Dartford · Folkestone · Dover · Margate and Thanet · Sevenoaks · Tonbridge · Tunbridge Wells · Erith · Bexley · Thurrock · Basildon · All areas