A step-by-step guide to a typical mezzanine project, from the first site survey to the day you start using your new floor, with realistic timings on site.
A mezzanine floor can double the usable space in part of your building, but it is still a construction project. Knowing what happens at each stage helps you plan around your operation and avoid surprises.
This guide walks through a typical installation by our own qualified installers, drawing on over 20 years designing and installing mezzanine floors.
Our installers fit about 50 square metres of mezzanine a day on a clear site.
Allow around one more day for staircases, handrails and other extras.
A 200 square metre floor with a staircase takes about a week on site.
We can work outside your normal hours where needed, at an extra charge.

The time on site is often the shortest part of the project. We plan the work around your operation, with phased working where needed and exclusion zones keeping your team safe while work continues nearby.
A project manager oversees your job from survey to handover, and our own installers keep work areas safe, tidy and clearly separated.
One of our team visits your premises to understand how you work and what you need the space for. We check the clear height to the roof, lights and services; the floor slab; existing columns, racking, doors, fire exits and sprinklers; forklift routes and where stairs and pallet gates could go; and how the floor will be used. Book yours through our contact page.
We draw up a layout of the floor showing the column grid, beams, deck, staircases, handrails, pallet gates and any fire protection. You review it, we check column positions against your racking and aisles, and we send a written quotation. See mezzanine design.
Calculations confirm the steel sections, connections and base plates are right for the agreed load. Where racking or machinery sits on the deck, point loads are checked too.
We prepare and submit the drawings, calculations and fire and escape details to a building control body, either your council or a registered building control approver. Read our planning permission and Building Regulations guide.
Once the design is approved and the order confirmed, the steelwork is made to the dimensions on the drawings, and the decking, stairs, handrails and gates are prepared.
We agree a programme with you covering clearing the area, delivery times and vehicle access, exclusion zones, any isolation of lighting, sprinklers or alarms, and site rules and inductions.
A steel mezzanine is a bolt-together structure, so installation is quicker and cleaner than traditional building work. Base plates are fixed to the slab, columns go up, beams are bolted in and the deck is laid. Staircases, handrails and pallet gates follow.
Where needed, a fire-rated suspended ceiling is fitted beneath the deck, with casings to columns and fascias to the edges. For office mezzanines we add partitioning, ceilings, doors and finishes, with lighting and power by our trusted electrical partners. Racking or shelving on the deck can go in at this stage too.
Building Control inspects the work to check it matches the approved drawings, including connections, stairs, handrails, guarding and fire protection. We carry out our own quality checks and snagging, and the completion certificate is issued once Building Control is satisfied.
We walk you through the finished floor and hand over the documents: as-built drawings, structural calculations and load rating, a safe working load notice on the mezzanine, the Building Regulations completion certificate, fire protection certificates where relevant, and guidance on use and inspection.

Insurers, landlords, buyers and future tenants may ask for your handover documents. If you are the responsible person under fire safety law, review your fire risk assessment now that the building has a new floor level.
Adding racking or shelving to the deck? We can arrange SEMA-approved inspections.
“Amazing work from Robbie and Lance very professional service would highly recommend…”
“Very good workers, accurate and well layed out designs, 2nd mez they have done for us…”
“Nxt Level recently installed our mezzanine and I honestly cannot recommend them highly enough…”
What drives the cost of a mezzanine, and how to compare quotes like for like.
Read the guideWhen planning permission applies and what Building Regulations cover.
Read the guidePart K and utility staircases, handrails, pallet gates, decking and protection.
Mezzanine ancillariesPhotos of recent mezzanine, racking and fit-out work across Kent, London and Essex.
See our projectsA Canterbury team with over 20 years designing and installing mezzanine floors.
About usCase studies: JLC Ltd (Jaguar Land Rover), Sevenoaks · Big Fish SRL, Horsmonden · Eurotunnel, Folkestone
Tell us about your building and what the floor is for, and we will arrange your free site survey and a clear programme. Prefer to talk? Call 01227 678 128 or 0330 133 2445.
Book a free site survey and we will give you a clear programme and a written quotation for your premises. Read about costs in our mezzanine floor cost guide. Call us Monday to Friday 8:00 to 17:30, closed weekends, or email info@nxtlevelgroup.co.uk.
Areas we cover: Canterbury · Ashford · Maidstone · Medway · Dartford · Folkestone · Dover · Margate and Thanet · Sevenoaks · Tonbridge · Tunbridge Wells · Erith · Bexley · Thurrock · Basildon · All areas
NXT Level Group Ltd, registered in England and Wales, company number 16699553. Trading address: 6-8 Longmarket, Canterbury CT1 2JS.